A recent federal district court ruling in Maryland has provided clarity on whether a design-builder can withhold payments to a design professional to recover costs associated with project delays. This litigation, involving Pontiac Drywall Systems Inc. was involved, though their vice president admitted they did not contribute to the 100% pre-final design submission delay. and Wiley & Wilson Inc., v. Pontiac Drywall Systems Inc.*, addressed whether contractual language restricting payment withholding prevents a contractor from seeking recoupment for actual damages.
In the project, Pontiac Drywall Systems Inc. (PDSI) acted as the design-builder for a U.S. Naval Academy renovation, contracting with the architecture firm Wiley & Wilson. The agreement stipulated that the architect would receive $1.The agreement totaled $1.125 million. Under the terms, PDSI could not withhold payments as a punitive measure or for liquidated damages. Such deductions required the architect’s consent or a formal finding of liability.
PDSI kept about $741,124 from 20 invoices after the design by Wiley & Wilson arrived 14 months past the due date. Wiley & Wilson filed suit to recoup those funds, but PDSI countered that the project delays generated $2.43 million in overhead expenses.43 million in extended overhead costs.
Summary judgment was sought by Wiley & Wilson, which contended that the withheld payments breached the contractual ban on penalties. The court rejected this request. It ruled that Maryland law permits parties to lower claims when the other side fails to fulfill duties linked to that specific deal. The court distinguished between punitive withholding—which was prohibited by the contract—and an attempt to recover actual, documented losses. Because PDSI presented evidence of overhead costs exceeding the unpaid invoices, the court found a triable factual dispute existed regarding whether the withholding was compensatory rather than punitive.
Additionally, the court rejected the architect’s argument that expert testimony was required to prove the breach of the schedule. Professional negligence cases usually need expert testimony on care standards. However, the court ruled that jurors can decide if a breach happened by looking at the major delay in meeting contractual deadlines.
The ruling emphasizes that contractual limitations on withholding must be drafted explicitly to cover all scenarios, including actual delay damages. Furthermore, it highlights the legal weight of project schedules, which can serve as the basis for breach-of-contract claims independent of professional liability theories. The ruling permits PDSI to continue its counterclaim, but it does not ensure a win. PDSI must still prove its right to recoupment during the upcoming trial.